1. It appears that the majority are actually items that TWJO select after the completion of the technical design and shall be incorporated in TWJO’s submission of the construction design viz method statement, shopdrawings, material approvals etc.
2. TWJO shall select such items (including proprietary products) to meet all the requirements stated in the drawings and specifications.
3. For such items, we shall not revise the technical design drawings or specifications as these is deemed to have the Engineer’s agreement as there is no comments to this effect. Currently, we would only address all the Engineer’s comments.
4. We note that in this respect TWJO’s change of construction sequence at this late stage may have implications of getting the Engineer’s approval.